Seven Seas Condo Resort Jomtien: Buildings C, D, E & H have now been topped-off whilst the scaffolding and sheet metal molds are in place in readiness for the subsequent pouring of the 8th floor of buildings B & F once workers have cut, shaped and spot-weilded the necessary rebar into place.

Similarly preparations are currently underway for the pouring of the 6th floor in building A and the 4th floor for building G. In addition the installation of the P.V.C water and waste water pipes remains ongoing whilst the construction of the internal cinder-block partitioning walls is still yet to begin